Golden Brick Explained
"Golden brick" describes a way of acquiring new homes part-way through construction. Homes England's Capital Funding Guide explains it as an arrangement where a provider typically enters a building contract for a new build scheme that will be transferred into its ownership at a partially built "golden brick" stage, before completion. The provider is then responsible for the works after the golden brick stage, whether it procures them from the seller or another contractor (Capital Funding Guide, chapter 10).
This guide explains how Homes England treats golden brick schemes for grant, drawing on chapter 10 (Finance) of the Capital Funding Guide, updated 21 August 2026.
How a golden brick arrangement works
The agreement for sale, or other legal agreement, typically includes a backstop date, allowing either completion of the acquisition or termination if the golden brick stage is not reached by then (Capital Funding Guide, chapter 10).
Golden Brick Secure Legal Interest
For grant purposes, Homes England defines a Golden Brick Secure Legal Interest as a binding contract between the provider and the owner of the site, under which the provider will later acquire a completed secure legal interest in the homes being built. The contract must meet four conditions (Capital Funding Guide, chapter 10):
- Legal completion of the transfer or lease to the provider takes place no earlier than the point at which the homes are "partly constructed buildings" as defined in paragraph 4.7.4 of HM Revenue and Customs VAT Notice 708, but before the homes reach practical completion.
- The site owner is responsible for building, or procuring the building of, the homes up to that transfer point.
- By the transfer point, the provider has, or will have, contractual arrangements in place to build or procure the homes through to practical completion.
- Unless Homes England agrees otherwise, the acquisition is conditional only on matters within the reasonable control of the site owner or the provider.
Grant on golden brick schemes
Homes England pays grant in tranches on the achievement of site acquisition, start on site and completion milestones (Capital Funding Guide, chapter 10). Normally a contractual interest, such as an agreement to acquire, is not a sufficient secure legal interest to claim grant. Golden brick is one of the exceptions, under specific conditions.
Continuous Market Engagement (CME)
Under certain AHP 2021 to 2026 and SAHP 2026 to 2036 CME grant agreements that support Golden Brick Schemes, a provider may claim the start on site tranche where (Capital Funding Guide, chapter 10):
- the scheme meets the agreement's definition of a Golden Brick Scheme or Golden Brick Delivery Phase;
- it is not a single claim (flex) scheme, and no acquisition tranche is claimed for it;
- start on site works have been achieved;
- the provider holds a Golden Brick Secure Legal Interest and will be entitled to a completed secure legal interest before practical completion.
The start on site claim can cover pre-golden brick and post-golden brick works, but together with any other grant paid on the scheme it must not exceed the eligible development costs actually incurred at the date of the claim. A provider without a grant agreement that supports Golden Brick Schemes cannot claim any grant until the golden brick transfer has happened and it holds a completed secure legal interest. Golden brick schemes are not eligible for the acquisition tranche (Capital Funding Guide, chapter 10).
Schemes where providers are in golden brick arrangements before start on site are also not eligible for CME flexibilities (Capital Funding Guide, chapter 6).
Strategic Partnerships
A Strategic Partner or Delivery Partner may make a site Active and achieve start on site under a golden brick arrangement, provided it holds the qualifying contractual interest set out in its grant agreement, start on site works have been achieved, and it will hold a full secure legal interest before practical completion. Development expenditure cannot be recorded against the site until that full interest is held (Capital Funding Guide, chapter 10).
Section 106 homes
Homes England grant cannot be used to acquire homes secured through Section 106 agreements or equivalent planning conditions (Capital Funding Guide, chapter 10).
Milestones and timing
At each grant claim, the provider warrants to Homes England that the relevant milestone has been achieved by the milestone date agreed in the digital system, that it holds a secure legal interest, and that the other claim conditions are met (Capital Funding Guide, chapter 10). If a milestone is never achieved, Homes England requires repayment of all grant paid for it, plus any interest due. If a milestone is achieved later than anticipated, it will normally require interest on the grant paid (Capital Funding Guide, chapter 7). On a golden brick scheme, the backstop date in the agreement for sale is a further date to manage.
Sequel, SDS's project management software, tracks milestones, budgets and costs for every scheme from approval to completion and flags variance against the approved appraisal (SDS). Organisations can configure their own project and workflow attributes (G-Cloud 14 listing).